THEC Letter of Notification Timeline
| Action | Timeline |
| APSU determines they would like a new program and begins work on the Letter of Notification (LON) |
|
| LON Submitted to Academic Affairs for first review | September/October Planning year 1 |
| Submit LON to THEC for initial approval | January: Planning Year 2 |
| Receive Final approval from THEC for the LON | May: Planning Year 2 |
| External Review | July/August: Planning Year 2 |
| Response to External Review | September/October: Planning Year 2 |
| Final approval from THEC to send to Board | October: Planning Year 2 |
| Placed on THEC Meeting agenda | November: Planning Year 2 |
| THEC Commission Approval | January: Implementation Year |
| Implement Program | August: Implementation Year |
* All new program should be implemented in the Fall term.