Physical Plant Zone Maintenance consists of a team of professionals dedicated to maintaining and improving campus-building conditions for the students, faculty and staff. The primary goal of zone maintenance is to provide dedicated response for maintenance and repair with “ownership” of the zone residing with the team. If the team confronts an issue that is beyond their abilities, it will be directed to the Director of Physical Plant for further review and action.
The campus will be divided into zones manned with maintenance personnel from Physical Plant. Each zone group consists of trades made up of electricians, carpenters, HVAC mechanics, plumbers and painters. Two zones groups are dedicated in maintaining the academic buildings, the third zone group will support student housing and the fourth group (Central Plant Support Team) will support all three-zone groups in the event they required additional support or replacing absent personnel.
All members of the team are responsible for the respective zone they are assigned in and thus are expected to assist each other in carrying out all the maintenance requirements of the zone. Each zone will be assigned a leader; the leader will identify work and create a list on what is to be accomplished for each building. Zone leaders also service as a liaison between Physical Plant and the building coordinator in getting the miscellaneous work accomplished, and are responsible for resolving roadblocks to success of the team.
This concept will allow Physical Plant to service the buildings twice a year.
Listed below are maintenance tasks typically performed by the Zone Maintenance groups.
Academic Building Service Schedule and how it operates:
Building Schedule:
Zone 1
The following buildings that included in this zone are: Browning, Clement, Claxton, Ford Street, Harned, Hemlock, Kimbrough, Marks, Music/Mass Communication, Sexton, Sundquist, Trahern, Woodward Library, Ft. Campbell, and APSU Farm.
Zone 1 PreventativeMaintenance Schedule | |
1. Sundquist Science | Aug 15 - Sept 9 |
2. Trahern | Sept 12 - Sept 23 |
3. Woodward Library | Sept 26 - Oct 7 |
4. Ft. Campbell | Oct 10 - Oct 21 |
5. Farm | Oct 24 - Oct 28 |
6. Browning | Oct 31 - Nov 4 |
7. Clement | Nov 7. - Nov 18 |
8. Claxton | Nov 21 - Dec 2 |
9. Ford Street | Dec 5. - Dec 9 |
10. Harned Hall | Dec 12 - Dec 23 |
11. Hemlock | Jan 2 - Jan 6 |
12. Kimbrough | Jan 9 - Jan 20 |
13. Marks | Jan 23 - Feb 3 |
14. Music/Mass Comm. | Feb 6 - Feb 24 |
15. Sexton | Feb 27 - Mar 2 |
For questions or concerns regarding Zone 1 contact supervisors Damaso Vega or Kenneth Butts.
Zone 2
The following buildings are included in this zone: CH Bookstore. Dunn Center, Ellington, Foy, McCord, McReynolds, Pace Alumni Center, Memorial Health, Shasteen, Stadium, Tennis Center, University Center, Power Plant, 325 Drane Street, Baseball, Warehouse, 601 N. 2nd Street, and 505 York Street.
Zone 2 - Preventative Maintenance
1. White House
Aug 29 - Sep 2
2. Foy Fitness Center
Sept 5 - Sept 16
3. Baseball/Warehouse
Sept 19 - Sept 23
4. McReynolds
Sept 26 - Oct 7
5. Dunn Center
Oct 10 - Oct 28
6. Shasteen
Oct 31 - Nov 11
7. Tennis Center/Stadium
Nov 14 - Nov 18
8. University Center
Nov 21 - Dec 9
9. McCord
Dec 12 - Jan 6
10. Pace Alumni
Jan 9 - Jan 13
11. 601 N. 2nd Ave
Jan 16 - Jan 20
12. 505 York Street
Jan 23 - Jan 27
13. Bookstore
Jan 30 - Feb 3
14. Memorial Health
Feb 6 - Feb 10
15. Ellington
Feb 13 - Mar 2
For questions or concerns regarding Zone 2 contact supervisors Mark McLain or Craig Sager.
Zone 3 - Housing
The buildings that included in the following zone are: Archwood, Blount, Castle Heights, Emerald Hills, Greek Village, Hand Village, Harvill Hall, Marion Street Apartments, Meacham Apartments, Miller, Sevier, and Two River Apartments.
Zone 3 - PreventativeMaintenance Schedule | |
1. Archwood | Aug 29 - Sept 2 |
2. Hand Village 100 | Sept 12 - Sept 16 |
3. Hand Village 200 | Sept 19 -Sept 23 |
4. Hand Village 300 | Sept 26 - Sept 30 |
5. Hand Village 400 | Oct 3 - Oct 7 |
6. Hand Village 500 | Oct 10 - Oct 14 |
| 7. Hand Village 600 | Oct 17 - Oct 21 |
| 8. Hand Village 700 | Oct 24 - Oct 28 |
| 9. Hand Village 800 | Oct 31 - Nov 4 |
| 10. Harvill Hall | Nov 7 - Nov 18 |
| 11. Emerald Hills 1 - 14 | Nov 21 - Dec 16 |
| 12. Two Rivers | Dec 19 - Dec 23 |
| 13. Blount Hall | Jan 2 - Jan 13 |
| 14. Sevier Hall | Jan 16 - Jan 20 |
| 15. Miller Hall | Jan 23 - Jan 27 |
| 16. Marion Street Apartments | Jan 30 - Feb 3 |
| 17. Castle Heights | Feb 6 - Feb 17 |
| 18. Meacham | Feb 20 - Mar 2 |
| 19. Greek Village | Mar 5 - Mar 9 |
For questions or concerns regarding Zone 3 contact supervisor Mike Ramsay.
Housing Service Schedule
All questions and concerns regarding Zone 3 should be emailed to Jan Ellis or call the Zone 3 work order line at 221-7424.
How the schedule Works:
Each building is setup for one (1) week of non-stop maintenance. If any work orders are generated during the time the zone group is in the building, the zone leader will complete all request if possible. The Central Plant Support Team group four will address all other work orders that are generated between schedule maintenance. If miscellaneous materials are required for any work that is requested during maintenance periods or between scheduled dates, Physical Plant will purchase the item and reschedule to completed work order.